Aboutthis project

Essentra Packaging 1

Client: Essentra Packaging
Designer: Tandem Project Management

This project delivered a re-configuration of an existing printing factory floor to facilitate the installation of new printing press. Scope included the following headline elements:

  • Demolition & strip out
  • Fabrication and installation of intermediate working cell screens
  • Excavation of existing factory floor & the construction of 600mm thick reinforced concrete floor base slab for printing press support
  • Water and HVAC services
  • Resin flooring works
  • Painting & decorating

Widespread electrical service modifications and rationalisation of existing electrical infrastructure were also completed to support new factory floor layout.