Aboutthis project
Client: Essentra Packaging
Designer: Tandem Project Management
This project delivered a re-configuration of an existing printing factory floor to facilitate the installation of new printing press. Scope included the following headline elements:
- Demolition & strip out
- Fabrication and installation of intermediate working cell screens
- Excavation of existing factory floor & the construction of 600mm thick reinforced concrete floor base slab for printing press support
- Water and HVAC services
- Resin flooring works
- Painting & decorating
Widespread electrical service modifications and rationalisation of existing electrical infrastructure were also completed to support new factory floor layout.