Client: Colaiste an Spioraid Naoimh
Designer: Murphy McCarthy Consulting Engineers
Replacement of existing 100mm ring distribution Watermain and combined sewer system serving a Secondary School facility.
Aggressive schedule required the works to be completed during school Summer Holiday period.
Scope included the following headline items:
- 350 lin.m of 110mm HDPE Watermain by trenchless pipe installation methods.
- Installation of Fire Hydrant, Sluice Valve and service connections to watermain
- 270 lin.m of 150mm dia. sewer pipe